Production manager handover

A departing production manager (responsable de production) hands their successor the settings of each line, the known breakdowns, the mandatory safety checks and the teams. Under French law, several of these checks have a fixed interval: companies with 11 or more employees update their occupational risk assessment document at least once a year1.

Open the handover template

1. The role and its scope

This page also applies to a plant manager (directeur d’usine), who also hands over the site’s budget and investments.

The lines, the teams and what depends on other departments.

  • The workshops, lines and product families under their responsibility.
  • The teams, shift patterns and headcount of each line.
  • What belongs to maintenance, quality, industrial engineering and safety.
  • For a plant manager, the site budget, the investments and the link with senior management.

2. The people

Who to call on the line, and outside the plant.

  • The team leaders and the setup technicians, with what each one can do alone.
  • The operators who know the settings for the difficult products.
  • The machine manufacturers, the subcontractors and the outside contractors who work on the site.
  • The elected members of the works council (comité social et économique, CSE), with the topics under way.
  • The ICPE-regulated facilities (classified installations) inspectorate (inspection des installations classées) and the labor inspectorate (inspection du travail), if they already oversee the site.

3. Tools and documents

Where the settings, the instructions and the figures are.

  • The setup sheets by product and by machine, with the date each was last updated.
  • The routings and bills of materials in the ERP, and where they are known to differ from reality.
  • The dashboards for output, scrap, downtime and accidents, with their source.
  • The safety register, the inspection reports and the occupational risk assessment document.
  • The prefectoral order (arrêté préfectoral) or the proof of declaration for the site’s ICPE-regulated facilities (classified installations) (installations classées pour la protection de l’environnement, ICPE), and the inspection reports.

4. Open files

What is open on the day of departure.

  • The breakdowns under way, the parts on order and the machines being monitored.
  • New product launches and planned line trials.
  • The investments committed, with the suppliers and the start-up dates.
  • The actions promised after an accident, an audit or an inspection visit.
  • The hiring, temporary staff and training planned before the next season.

5. The calendar

What recurs on a fixed date. These are general rules under French law; check how they apply to the site.

DeadlineWhen
Update of the occupational risk assessment document (document unique d’évaluation des risques, DUERP)At least once a year, in companies with 11 or more employees1.
Periodic general inspection of lifting equipmentEvery 6 months for forklifts. Every 12 months for most other lifting equipment2.
Written prevention plan (plan de prévention) with an outside contractorBefore the work starts, if it is expected to total at least 400 hours over 12 months or less, or is classified as hazardous3.
Periodic inspection of a classified facility subject to declaration with inspectionAt least once every 5 years, or every 10 years if the environmental management system is ISO 14001 certified by an accredited body. No such inspection if the site also has a facility subject to authorization or registration4.
Maintenance shutdowns and product changeovers for the seasonInternal dates, in the production plan.
Customer audits and certification auditsDates set with the quality department (internal).

6. Decision paths

Who stops a line, who restarts it, who invests.

  • Who can stop a line for a quality defect or a safety risk.
  • Who decides on overtime, weekend shifts and the use of temporary staff.
  • Who decides between two orders when capacity runs short.
  • The amount up to which the manager commits a repair or investment alone.

7. Problems and pitfalls

What the successor discovers at the first breakdown.

  • Settings that a setup technician keeps in their head, missing from the setup sheets.
  • The machine that runs on a temporary repair, and the part never replaced.
  • The products that only run well on one line, or with one team.
  • Tolerances accepted verbally by the quality department or by a customer.
  • The retirements coming up among setup technicians and team leaders.

8. History and next steps

What has already been decided, and what awaits the successor.

  • The workplace accidents of recent years, and the measures taken.
  • The investments refused or postponed, and the reasons.
  • The productivity trials abandoned, and why.
  • The priorities for the first month, starting with the most fragile line.

Plant audit checklist: every month

The departing manager fills it out with the successor, noting where each record is kept.

Bridger uses your address to send you this file. Privacy and your rights

Every month

Plant audit checklist: every year

Every year

Questions to ask the departing production manager

These questions are specific to production. The 40 questions to ask your predecessor cover every role.

  • Which plant decisions do you make alone, without senior management?
  • Which setup technician or operator is the only one who can set up a line?
  • Which setup sheets no longer match practice?
  • Which machine is likely to break down this quarter?
  • When are the next equipment inspections, and the next periodic inspection of the ICPE-regulated facilities (classified installations)?
  • Who can stop a line while you are away?
  • Which tolerance was accepted verbally, and by whom?
  • Which investment needs defending at the next budget?

Frequently asked questions

How do you prepare a plant audit after a departure?

Start with the figures of the last six months, line by line, then go to the shop floor. Compare the setup sheets and instructions with what the teams actually do. Finish with the safety registers, the inspection reports and the actions promised to the inspectorate.

What does an internal audit of production processes check?

An internal process audit follows one product from order to shipment. At each step, it checks that there is a written instruction, a person responsible and a measurement. After a departure, it quickly shows which steps relied on the departing manager.

Do you need an interim manager to replace a plant manager?

Yes, if the site has no deputy able to make the safety and investment decisions: an interim manager then makes them. Otherwise, a production manager can cover in the meantime, with the list of breakdowns, upcoming inspections and committed projects.

Read next

Sources

  1. [1] Service Public Entreprendre, “Qu’est-ce que le document unique d’évaluation des risques professionnels (DUERP) ?” (“What is the occupational risk assessment document (DUERP)?” in French), page checked by the administration on July 22, 2026, accessed on November 3, 2026. entreprendre.service-public.gouv.fr
  2. [2] Légifrance, Arrêté du 1er mars 2004 relatif aux vérifications des appareils et accessoires de levage, articles 20 et 23 (order of March 1, 2004 on inspections of lifting equipment, in French), version in force since March 31, 2005, accessed on November 3, 2026. legifrance.gouv.fr
  3. [3] Légifrance, Code du travail (French Labor Code), article R4512-7 (written prevention plan with an outside contractor, in French), version in force since May 1, 2008, accessed on November 3, 2026. legifrance.gouv.fr
  4. [4] Légifrance, Code de l’environnement (French Environmental Code), articles R512-55 to R512-60 (periodic inspection of facilities subject to declaration, in French), version in force since December 2, 2018 (R512-55) and November 10, 2011 (R512-57), accessed on November 3, 2026. legifrance.gouv.fr