Supply planner handover
A departing supply planner (approvisionneur, also called a buyer-planner) hands over the open orders, the suppliers to chase, their stock settings and the items on watch. Two traps sit in those settings: lead times in the ERP that are shorter than the real ones, and the margin the planner allowed for suppliers who miss their dates.
Contents
1. The role and its scope
The items the planner manages, and where the buyer’s role begins.
- The item families managed, from raw materials and packaging to purchased finished goods.
- The sites and warehouses supplied, and the service level expected for each one.
- What the buyer does and what the supply planner does, from negotiation to follow-up.
- The orders generated by the ERP’s material requirements planning (MRP), and those placed by hand.
2. The people
Who answers at each supplier, and inside the company.
- The person who confirms dates at each supplier, often its sales administration team.
- The contacts at the factory or the sourcing office for products made in Asia.
- The production planner and the warehouse manager, to notify of every delay.
- Receiving inspection, and accounts payable for invoice discrepancies.
3. Tools and documents
Where the orders, the lead times and the settings are kept.
- The ERP, the MRP run and the order suggestions that the departing planner approves or corrects.
- The lead times, minimum order quantities and pack multiples entered for each item.
- The supplier portals and EDI exchanges, with the access opened in the departing planner’s name.
- The order and follow-up tracking file, if it lives outside the ERP.
4. Work in progress
What is open on the day they leave.
- Unconfirmed orders, and those whose confirmed date has passed.
- Items out of stock or close to it, and the emergency supplies already arranged.
- Receipts in dispute for shortages, breakage or non-conformity, and the reservations (réserves) and protests already sent.
- Packaging or item code changes under way, and the old-version stock still to use up.
5. Key dates
What comes back on a fixed date. General rule under French law: check it against your company’s situation.
| Deadline | When |
|---|---|
| Protest to the carrier for damaged or missing goods | A reasoned protest within the 3 days following receipt, public holidays not counted, by registered letter or by bailiff’s notice (acte extrajudiciaire). For international transport, other rules may apply1. |
| MRP run and order placement | Internal cadence, every day or every week. |
| Supplier factory closures, such as Chinese New Year and summer shutdowns | Dates to plan ahead in the order schedule. |
| Cycle counts and the annual physical inventory count (inventaire) | Internal dates, set with the warehouse and accounting. |
6. Who decides what
Who approves an order, an emergency supply or a discrepancy.
- The amount above which an order needs the signature of the buyer or the manager.
- Who can accept a delivery postponement or a partial delivery.
- Who decides on express transport, and which budget pays for it.
- Who can change a safety stock or a lead time in the ERP.
7. Problems and pitfalls
What the successor discovers at the first stock-out.
- Suppliers who confirm a date without meeting it, and the margin the departing planner used to allow.
- Lead times entered in the ERP that are shorter than the real ones.
- Orders placed early out of habit, before a season or a factory closure.
- Components shared by several products, whose stock-out stops several lines.
- Arrangements obtained by phone, with no trace in the ERP.
8. History and next steps
What has already been decided, and what is waiting for the successor.
- The stock-outs of recent months, their cause and what has changed since.
- The items moved to two suppliers, and those still single-sourced.
- The stock settings that were reviewed, with the date and the reason.
- First-month priorities, starting with the unconfirmed orders.
Supply planner handover checklist
The departing planner fills it out before leaving and notes where each piece of information is kept.
Every week
Supply planner checklist: every year
Every year
Questions to ask the departing supply planner
For every role, see also the 40 questions to ask your predecessor.
- Which items do you order outside the MRP run?
- At which supplier should I call someone else to get a reliable date?
- Which lead times or minimums entered in the ERP are wrong?
- Which orders need chasing this week?
- Which orders do you place early because of a season or a closure?
- Up to what amount do you order without another signature?
- Which shared component could stop several lines?
- Which recent stock-out could happen again, and why?
Frequently asked questions
What is the difference between a buyer and a supply planner?
The buyer chooses the suppliers and negotiates prices and contracts. The supply planner places the orders within that framework, tracks lead times and chases suppliers. In a small or midsize company, the same person often does both, and the handover must then cover both roles.
How do you calculate safety stock?
Several methods exist. The simplest covers the supplier’s usual delay, expressed in days of consumption. Statistical methods also take into account the variation in sales and lead times. When the supply planner leaves, write down the method used and the date of the last calculation.
The supply planner left without a handover. Where do you start?
Export the list of open orders from the ERP, sorted by delivery date. Call the suppliers of unconfirmed or late orders. Then cross-check with the items below safety stock. These three lists cover the first few weeks.