Maintenance manager handover

A departing maintenance manager (responsable maintenance) hands their successor the breakdown history, the list of critical spare parts, the maintenance contractors and the calendar of periodic inspections. Under French law, some inspections have a fixed interval, such as every 6 months for forklifts1.

Open the handover template

1. The role and its scope

The CMMS (computerized maintenance management system, GMAO in French) keeps the work orders. The settings, the troubleshooting tips and the repair technicians’ contact details often stay in the departing manager’s emails and memory.

The equipment covered, and what is subcontracted.

  • The lines, the machines and the utilities of each site: compressors, boiler room, refrigeration, electrical systems.
  • The share of the work done by the in-house team, and the share given to contractors.
  • The most critical equipment, whose breakdown stops production or shipping.
  • The new installations and projects that maintenance follows.

2. The people

Who to call about a breakdown, a part or an inspection.

  • The technicians, their skills, their electrical safety authorizations (habilitations électriques) and their on-call duty.
  • The maintenance contractors, with the contact to call at night and on weekends.
  • The machine manufacturers, and the technician who knows each model.
  • The inspection body that carries out the periodic inspections, and the usual contact there.
  • The spare parts suppliers, and those who deliver in an emergency.

3. Tools and documents

Where the history, the drawings and the access rights are.

  • The CMMS, the preventive maintenance plans and the rules for logging work orders.
  • The technical files of the machines: manuals, wiring diagrams, PLC programs.
  • The backups of the PLC programs, with the version running on each machine.
  • The register of periodic inspections and the inspection bodies’ reports.
  • The maintenance contracts, with their end dates and notice periods.

4. Open files

What is open on the day of departure.

  • Recurring breakdowns whose cause has not been found.
  • The observations in the latest inspection reports, and the work promised.
  • The parts on order, with their lead times.
  • The planned shutdowns, and the work to do during the vacation period.
  • The investment requests waiting for a decision.

5. The calendar

What recurs on a fixed date. These are general rules under French law; check how they apply to your company.

DeadlineWhen
Periodic general inspection of forkliftsEvery 6 months. Every 12 months for most other lifting equipment1.
Periodic inspection of electrical installationsEvery year. The head of the establishment may extend this to 2 years if the previous report has no observations, or if the work it required was done before the due date. The labor inspector (inspecteur du travail) must then be informed by registered letter2.
Servicing and inspection of automatic doors and gatesAt least every 6 months, and after any breakdown. Each intervention is recorded in the maintenance logbook3.
Written prevention plan (plan de prévention) with an outside contractorBefore the work starts, if it is expected to total at least 400 hours over 12 months or less, or if the work is on the official list of hazardous work4.
Annual technical shutdownsDates set with production (internal).

6. Decision paths

Who decides to stop, repair or replace.

  • Who can stop a line for an intervention, and who restarts it.
  • Up to what amount the maintenance manager orders a part or a repair alone.
  • Who chooses between repairing and replacing a machine.
  • Who locks out an electrical installation, and who authorizes hot work.

7. Problems and pitfalls

What the successor discovers at the first major breakdown.

  • Settings and troubleshooting tips known to a single technician.
  • Critical parts with no safety stock and a lead time of several weeks.
  • Machines whose manufacturer has disappeared or no longer supplies parts.
  • PLC programs changed without a backup of the latest version.
  • Interventions never logged in the CMMS, and therefore missing from the history.

8. History and next steps

What has already been decided, and what awaits the successor.

  • The major breakdowns of recent years, their cause and their cost.
  • The contractors the company has dropped, and why.
  • The investments postponed, and the risks accepted in the meantime.
  • The priorities for the first month, starting with the recurring breakdowns and the next shutdown.

Maintenance audit checklist: every month

The departing manager fills it out with the successor, noting where each record is kept.

Bridger uses your address to send you this file. Privacy and your rights

Every month

Maintenance audit checklist: every year

Every year

Questions to ask the departing maintenance manager

These questions are specific to maintenance. The 40 questions to ask your predecessor cover every role.

  • Which machines stop the whole site when they break down?
  • Which technician or contractor knows each critical machine best?
  • Where are the backups of the PLC programs?
  • Which breakdowns keep coming back with no cause found?
  • When are the next periodic inspections due?
  • Who can decide to stop a line while you are away?
  • Which part would be most missed in a breakdown, and what is its lead time?
  • Which investment would you have made first?

Frequently asked questions

What questions should a maintenance audit ask?

Are the critical machines identified, and do they have a preventive plan that is followed? Are the critical parts in stock? Are interventions logged in the CMMS? Are the periodic inspections up to date, and their observations cleared? The checklist on this page covers these points.

What does a preventive maintenance plan contain?

For each piece of equipment, a preventive maintenance plan lists the tasks, their frequency, who does them and the time planned. Add the parts to have on hand and the safety instructions. A plan that is not in the CMMS, or no longer followed, is lost at the first departure.

Do you need an interim maintenance manager?

An interim manager makes sense if no technician can run the department, if a technical shutdown is coming up or if breakdowns are multiplying. Otherwise, the priority goes to the critical machines, the parts with no stock and the inspections falling due.

Read next

Sources

  1. [1] Légifrance, Arrêté du 1er mars 2004 relatif aux vérifications des appareils et accessoires de levage, articles 20 et 23 (order of March 1, 2004 on inspections of lifting equipment, in French), version in force since March 31, 2005, accessed on November 3, 2026. legifrance.gouv.fr
  2. [2] Légifrance, Arrêté du 26 décembre 2011 relatif aux vérifications des installations électriques, article 3 (order of December 26, 2011 on inspections of electrical installations, in French), version in force since December 30, 2011, accessed on November 3, 2026. legifrance.gouv.fr
  3. [3] Légifrance, Arrêté du 21 décembre 1993 relatif aux portes et portails automatiques et semi-automatiques sur les lieux de travail, article 9 (order of December 21, 1993 on automatic doors and gates in the workplace, in French), version in force since May 1, 2008, accessed on November 3, 2026. legifrance.gouv.fr
  4. [4] Légifrance, Code du travail (French Labor Code), article R4512-7 (written prevention plan with an outside contractor, in French), version in force since May 1, 2008, accessed on November 3, 2026. legifrance.gouv.fr